INSTRUMENTACIÓN Y COMPONENTES
Download PDF

 

Direction:

C/ Alaún, 8 50197 Zaragoza (España)
Fecha: 02/04/2013

Contact:

José Manuel Martín Rapún
976 013 300
josemanuel.martin@inycom.es
C/ Alaún, 8 50197 Zaragoza (España)

Presentation

Ubication: C/ Alaún, 8 50197 Zaragoza (España)
Year of creation: 2009
managed power: 740 kW[1]
Description:The microgrid is located in the premises of the Aragon Hydrogen Foundation and other faci- lities within the Walqa park, which hosts one of the SINTER project demonstrators.
supports visits: Si
Function Microred: Si [2]
Island funtion: No

TYPE OF SERVICES:
  • Real environment

Description

The microgrid is located in the premises of the Aragon Hydrogen Foundation and other faci- lities within the Walqa park, which hosts one of the SINTER project demonstrators. It is made up of three wind turbines and PV panels for renewable energy generation, a small storage system, consumption loads (the buildings in the park) and a connection to the main grid.

Services offered
Projects and tests can be carried out once permission is granted by the Aragon Hydrogen Foundation.


[1] It is understood that managed power that is able to manage the control of the infrastructure. In laboratories without physical equipment (simulators, systems) This field does not apply.
[2] Microrred function if there are loads in the same location, generators and optionally storage, with integrated management of the whole.
 
 

EQUIPMENT

Consumer equipment

 

Type of load

 

Voltage level

 

Power

 

Connection type

Buildings of the Technology Park

 

15kV

 

>1MW

 

Direct

 

Storage Equipment

 

Storage technology

 

Voltage level

 

Power

 

Connection type

 

410 SAFTSBH 12 batteries

 

400V

12Ahof capacityto1 V

 

Converterstages

 

Experimental storage in hydrogen

 

400V

Electrolyzerof60kw

 

Converterstages

 

 

Generation control equipment

 

Generation technology

 

Voltage level

 

Power

 

Connection type

Enercon wind turbine

400V

330kw

Direct

Lager way wind turbine

400V

80kw

Direct

Vesta swind turbine

400V

225kw

Direct

5 photovoltaic modules

400V

100kw

Inverters

 

Simulation control equipment

The battery storage system can be managed by means of the voltage setpoint in order to en- sure that the power fed to the electrolyser remains stable

 
 

ELECTRIC SCHEME / IMAGES


 

KNOWLEDGE

Human resources
 
Permanent personnel
 

Academic Qualification

Number

of Professionals

Average experience  years

 

Knowledge areas

Bachelor of Physics

1

8

RES,GD,TIC

Industrial Engineer

1

8

EPOT,SEN,CI,CABLE

IT Engineer

4

6

RES,VE,SEN,TIC,BAT

 



Knowledge areas: Demand Management (GD), integration of renewable and distributed energy resources (RES), protection and network automation (AUTO), electric vehicle (EV), power electronics (EPOT), storage ( BAT), sensors (SEN), life management (lIFE), smart meters (CI), transformers (TRAFO), conductors (CABLE), information and communication technologies (ICT)
 

PROJECTS


Acronym-Name

Ambit

Initial/end Year

web

Total budget

Knowledge area

 

 

 

 

SINTER

 

 

 

 

National

 

 

 

 

2009/2011

 

 

 

 

www.sinter.es

 

 

 

 

3.47M€

RESAUTOEPOTBAT TICSEN

 

 

 

GEBE

 

 

 

National

 

 

 

2010/2012

 

 

 

www.gebe.sinter.es

 

 

 

2.5M€

GDRESEPOTBAT TICCI

 

 

 

 

ELYGRID

 

 

 

 

European

 

 

 

 

2012-2014

 

 

 

 

www.elygrid.com

 

 

 

 

3.75M€

BATTICRESSENCITICRES

AIRE

National

 

 

743,000M€

 

 


[5] Regional, National, European, …
 
 

Future plans

To use the facility as a demonstrator for European projects.
 
To add a distributed control software based on a multi-agent system.